Under Construction
"The Hideaway"
Currently Under Construction
Week of March 25, 2002 - excavation of foundation and pouring of concrete footers
April 1 - 12, 2002 - foundation/blockwork completed for basement-logs are custom cut and installed
over the sub floor
April 22 - 26, 2002 - The roof sheeting and insulation panels are now being installed as the cabin is now close
to the "dry in" stage
May 1 - 16, 2002 - The covered front porch is added, the roof tin is on and the exterior stain is applied.
May 17 - June 1, 2002 - Deck is completed and all windows and doors are installed. This completes the exterior
and now we will move inside to complete the interior.
July 2002 - All of our interior tongue & groove walls and
ceilings are now installed along with the log stair rails and
glass panels. We've also
finished the hardwood floors and hand made kitchen cabinets.
We have just finished mulching around the cabin and installing a gravel driveway. The Hideaway is now completed and
ready to move in to! Please call or email for more details!